Work continues on the second phase of the 91ÂÛ̳’s Education 2020 Capital Project, which was approved by voters in March 2022, and reauthorized in May 2023.
Currently site work is taking place at the Morgan Road Complex.
As of last week, 95% of the retention pond behind the building has been completed. Workers anticipate finishing the retention pond the week of July 1 and beginning the installation of an 18-inch drainage swale, as well as preparing the new headwall and pouring the footer.